top of page

Indonesia Foreign Test Lab Recognition Ends 31 Dec 2026

12 hours ago
4 min read

Indonesia Foreign Test Lab Recognition: Komdigi Non-MRA Lab Designations End on 31 December 2026


Indonesia foreign test lab recognition changes in six weeks. The designation of foreign testing laboratories through the non-MRA mechanism, which many manufacturers use for their Komdigi telecom equipment certifications, ends on 31 December 2026. From 1 January 2027, new test reports will have to come from Indonesian laboratories or from foreign laboratories designated under a mutual recognition agreement (MRA).


Background: how Indonesia designates test labs


Telecom equipment sold in Indonesia needs a certificate from the Ministry of Communication and Digital Affairs (Komdigi), issued through the Directorate General of Digital Infrastructure (DJID, formerly SDPPI). Certificates are based on test reports from designated laboratories.

Minister of Communication and Informatics Regulation No. 5 of 2024 (Permenkominfo 5/2024), set on 12 September 2024, rebuilt the designation system. Domestic labs are designated directly. Foreign labs normally come in through an MRA, with the partner country's designating body handling the application. The regulation also opened a temporary non-MRA route for foreign labs in countries that have no MRA with Indonesia. Only labs that had already been recognised before the regulation took effect could use it, and they had to apply by 1 November 2024 with ISO/IEC 17025 accreditation from an APAC-MRA or ILAC-MRA signatory.

Komdigi then issued Decree No. 13 of 2025 (Kepmenkomdigi 13/2025) on 15 January 2025. It lists the foreign labs designated through the non-MRA route and confirms that their test reports can support certificate applications. DJID announced on 20 February 2025 that the decree applies from 1 January 2025 to 31 December 2026. It replaced the earlier DG SDPPI Decision No. 109 of 2024.


Infographic summarizing Indonesia's Komdigi foreign test lab recognition changes, showing a timeline where non-MRA lab designations end on 31 December 2026, new rules requiring Indonesian or MRA-designated labs take effect on 1 January 2027, and existing non-MRA reports expire after a 6-month grace period around 30 June 2027, alongside an action checklist for manufacturers and a summary table of certification impacts.

Key Changes in the Indonesia Foreign Test Lab Recognition Rules


The non-MRA route closes on 31 December 2026

Article 27(4) of Permenkominfo 5/2024 says a non-MRA designation is valid until 31 December 2026. The decree's own validity ends on the same day. We haven't found any Komdigi notice extending it. From 1 January 2027, a test performed at a lab that relied on the non-MRA route won't count as a designated-lab test.


Existing reports get six months

Article 41 lets test reports from a domestic or foreign lab be used for certification for up to six months after the lab's designation is revoked, its scope extension is cancelled or its designation expires. For labs whose non-MRA designation ends on 31 December 2026, that points to about 30 June 2027. The grace period covers reports that already exist. It doesn't allow new testing at those labs in 2027.


Renewal only through an MRA

Renewal or scope extension of a foreign lab designation is handled through the MRA partner (Article 23). Komdigi can also revoke a non-MRA designation once an MRA applies in the lab's country, under the decree. A lab whose designation is revoked can only reapply after one year (Article 35).


What This Means for Manufacturers


  • Any certification plan that relies on a foreign lab outside an MRA needs a new testing route for 2027.

  • Tests that can be finished at your current lab should be completed, with reports issued, before 31 December 2026.

  • Certificate applications that use those reports should be filed well before the end of June 2027. Applications still in progress at that point may need new reports.

  • New products planned for launch in 2027 should be booked with an Indonesian designated lab or an MRA-designated foreign lab.

  • Domestic lab capacity may tighten in early 2027 as more work moves into Indonesia, so lead times are worth checking now.

  • Confirm your lab's status directly. Some labs may already be designated through an MRA, which isn't affected.


Certification Impact Summary


Area

Before

After

Impact level

Foreign labs in non-MRA countries

Designated under Kepmenkomdigi 13/2025

Designation ends 31 December 2026

High

New testing from 1 January 2027

Non-MRA, MRA or Indonesian labs

MRA-designated foreign labs or Indonesian labs only

High

Existing non-MRA test reports

Accepted for certification

Usable for up to six months after the designation ends (about 30 June 2027)

Medium

Renewal of a non-MRA designation

Not available outside the 2024 application window

Only through an MRA partner

Medium

MRA-designated foreign labs

Accepted

Unchanged

Low

Indonesian designated labs

Accepted

Unchanged; demand likely to rise

Medium


Timeline and Required Actions


Key Dates


Date

Milestone

12 September 2024

Permenkominfo 5/2024 set

1 November 2024

Deadline for foreign labs to apply through the non-MRA route

15 January 2025

Kepmenkomdigi 13/2025 set (applies from 1 January 2025)

31 December 2026

Non-MRA foreign lab designations end

1 January 2027

New tests must come from Indonesian or MRA-designated labs

About 30 June 2027

Six-month grace period for existing non-MRA test reports ends


Required Actions for Manufacturers


  1. List the Indonesian certifications and planned projects that use test reports from foreign labs.

  2. Check whether each lab is designated through an MRA or through the non-MRA route under Kepmenkomdigi 13/2025.

  3. Complete open testing at non-MRA labs and get the reports issued before 31 December 2026.

  4. File certificate applications that rely on those reports early, and track them against the end of June 2027.

  5. Book 2027 testing with an Indonesian designated lab or an MRA-designated foreign lab, and confirm lead times.

  6. Update launch plans and budgets for products whose Indonesian testing will move in-country.


Conclusion


The end of the non-MRA route is a fixed date in Permenkominfo 5/2024, and the six-month report window gives only limited room after it. Manufacturers that check their lab arrangements now can finish testing on time and move 2027 work to an accepted lab without delaying launches. Contact our team, and the agency in Indonesia, for help planning Komdigi certifications around the change.