Chile SEC portable power station certification is now set in law. On 21 October 2026, the Superintendency of Electricity and Fuels (SEC) signed Exempt Resolution No. 42708, approving protocol PE N°8/12:2026 for the safety certification of portable power stations. From 2 November 2027, manufacturers and importers will need an SEC safety approval certificate before they sell these products in Chile.


Background: why portable power stations are being added


Chile requires many electrical products to carry an SEC approval certificate under Supreme Decree No. 298 of 2005, the regulation on certification of electrical and fuel products. Each product needs a protocol that sets the standard, tests and certification system.

Portable power stations weren't on the list. On 24 June 2026, Exempt Resolution No. 44 (published in the Diario Oficial on 4 July 2026) added "portable power station with batteries" as a product that must hold an approval certificate before it's sold, in the safety area. SEC consulted on a draft protocol from 13 May to 16 July 2026 and its technical committee reviewed it on 1 September 2026. The final protocol is dated 2 October 2026.


Key Changes in the Chile SEC Portable Power Station Certification


One reference standard

The protocol uses IEC 62368-1:2018 (Edition 3.0), the safety standard for audio/video, IT and communication equipment. In the consultation draft, the test list covers electrical, fire, chemical, mechanical and thermal hazards, abnormal and single-fault conditions, Annex M for batteries and protection circuits, components, clearances, heat and fire resistance, mechanical strength and plug dimensions.


Which products are covered

The draft defines a portable power station as a compact, transportable unit that stores and supplies electricity, with a battery pack, an inverter and several AC and DC outputs in one enclosure. It covers products with a rated output of 6.0 kW or less, charged from the grid or from DC sources such as solar panels or vehicle adapters. Fuel generators, backup systems built from separate inverters and external battery banks, expandable modular systems, traditional UPS and power banks made only for mobile devices are excluded.


Two application dates

From 2 November 2027, manufacturers and importers must hold the safety certificate before a product is first sold, and any import after that date needs a certificate before sale. Retailers may keep selling uncertified units imported or bought before 2 November 2027 until 1 May 2028, provided they can document the import or purchase date. From 1 May 2028, every covered product on sale must have a valid certificate.


Infographic summarizing Chile SEC Portable Power Station Certification Protocol PE N°8/12:2026. It displays key compliance milestones—October 2, 2026 (final protocol), November 2, 2027 (mandatory certificate before first sale), and May 1, 2028 (all retail units certified)—alongside an illustration of a portable power station with an SEC mark, a map of Chile, and key requirements including standard IEC 62368-1:2018, component testing, and product marking.

Early certification and foreign certificates

Products can be certified early once SEC has authorised certification bodies for the protocol. Until then, foreign certificates can be used to request a sales authorisation under Article 9 of DS 298/2005.


Marking

The draft asks certification bodies to check IEC 62368-1 Annex F markings, the month and year of manufacture or a serial number on the product body, the country of manufacture and the SEC certification mark.


What This Means for Manufacturers


  • Portable power stations need an SEC certificate route planned well before November 2027.

  • IEC 62368-1:2018 test reports should cover the full test list, with special attention to Annex M battery tests.

  • Critical components such as cells, the BMS, PCB, fuses and thermal protections are recorded, so component data and certificates should be ready.

  • Labels may need the production date or serial number, the country of origin and space for the SEC mark.

  • Importers should document import dates for stock that will still be on sale after 2 November 2027.

  • Products near the scope limits, such as expandable systems, UPS-style units and large power banks, need a scope check.


Certification Impact Summary


Area

Before

After

Impact level

SEC certificate

Not required for portable power stations

Required before first sale from 2 November 2027

High

Reference standard

None set by SEC

IEC 62368-1:2018 (Edition 3.0)

High

Products already in the retail chain

No restriction

Uncertified stock imported before 2 November 2027 can be sold until 1 May 2028

Medium

All products on sale

No certificate

Valid certificate required from 1 May 2028

High

Product marking

General rules

Annex F markings, date or serial number, origin and SEC mark (per draft)

Medium

Foreign certificates

Not applicable

Can support a sales authorisation while no SEC body is authorised

Low


Timeline and Required Actions


Key Dates


Date

Milestone

13 May – 16 July 2026

Public consultation on the draft protocol

24 June 2026

Resolution No. 44 makes portable power stations a certified product (Diario Oficial, 4 July 2026)

2 October 2026

Final protocol PE N°8/12:2026 dated

21 October 2026

SEC Resolution No. 42708 approves the protocol

2 November 2027

Certificate required for manufacturers and importers before first sale

1 May 2028

All covered products on sale must be certified


Required Actions for Manufacturers


  1. Check which of your products fall within the scope, including the 6.0 kW limit and the exclusions.

  2. Review IEC 62368-1:2018 test reports against the protocol's test list, or plan new testing.

  3. Gather data and certificates for critical components, including the cells and the BMS.

  4. Update labels for production date or serial number, country of origin and the SEC mark.

  5. Watch for SEC's authorisation of certification bodies, and certify early if it suits your launch plan.

  6. Agree with importers how stock bought before 2 November 2027 will be documented.


Conclusion


The new Chile SEC portable power station certification gives manufacturers a year to prepare, with a single IEC 62368-1 test basis and two clear deadlines. Planning testing, component documentation and labels now will avoid a rush once certification bodies open for applications. Contact our team, and the agency in Chile, for support with SEC certification.


bottom of page