top of page

Taiwan BSMI Lithium Battery Inspection: 2028 Rules

13 hours ago
4 min read

Taiwan BSMI Lithium Battery Inspection: Power Banks, Cells and Packs Face New Rules from 2028


Taiwan BSMI lithium battery inspection rules changed on 17 November 2026. The Bureau of Standards, Metrology and Inspection (BSMI) published Announcement No. 11530023930 in the Executive Yuan Gazette, amending the inspection requirements for lithium power banks and related products. The notice took effect immediately, but its main deadlines fall in 2028.


Background


BSMI says the amendment aligns the power bank and lithium battery rules with updated international and national standards. It also widens the scope because lithium batteries carry a higher risk and are used so widely. Power banks were already subject to mandatory inspection in Taiwan. The new notice sets updated standards for them and lists nine product items in total.


Key Changes in the Taiwan BSMI Lithium Battery Inspection Rules


Wider scope

The notice brings these products into, or extends their coverage under, mandatory inspection:


  • dedicated portable lithium chargers up to 160 Wh, such as charging cases for earbuds, hearing aids, smart rings, watches, glasses, head-mounted displays, wireless microphones and styluses, where the charger has no universal interface like USB, Lightning or a DC jack

  • lithium jump starters

  • lithium cells, except button cells

  • lithium packs, modules and battery systems up to 100 kWh, excluding road-vehicle, e-motorcycle, e-bike, energy storage, rail, ship and manned-aircraft uses

  • non-traction lithium packs for road vehicles with two or more wheels


For products newly added to the scope, inspection of imports and domestic production starts on 1 January 2028. Manufacturers can choose Registration of Product Certification (RPC) or Type Approval with batch inspection, and BSMI is already accepting applications.


Infographic titled "Taiwan BSMI Lithium Battery Inspection: New Rules from 2028" outlining the expanded product scope (power banks, dedicated chargers, jump starters, cells, and packs up to 100 kWh), key compliance deadlines from November 2026 to July 2028, and five required manufacturer actions including safety testing and RoHS marking.

Power bank standards

Power banks up to 18 kg that aren't fixed equipment, or that have wheels, must meet CNS 15598-1 (2020), CNS 15936 (2016) or, with wireless charging, CNS 13803 (2018), and CNS 62133-2 (2018) or CNS 62619 (2020 or 2023). Power banks up to 160 Wh also need the CNS 62133-2 nail-penetration test (Annex G) or the forced internal short-circuit test (clause 7.3.9), carried out on the cells inside. The forced internal short-circuit test must be done by a BSMI-designated lab.


Battery systems, propagation and functional safety

Packs below 1 kWh can use CNS 62133-2 or CNS 62619. From 1 kWh to 100 kWh, only CNS 62619 applies. Power banks, cells and packs (items 1, 4 and 5) need the CNS 62619 propagation test. Their functional safety evidence must come from IEC/UL 60730-1 Annex H, IEC 61508 (SIL 2 or higher), ISO 13849 (performance level c) or UL 991 and UL 1998, through ILAC, IAF or IECEE-recognised bodies.


Marking

Power banks, dedicated chargers and jump starters must show their restricted-substance content under CNS 15663 section 5, on the product, packaging, label or manual, or through a stated web address. The commodity inspection mark includes the RoHS indication.


What This Means for Manufacturers


For power banks, the big date is 30 June 2028. Current certificate holders must submit documents against the new standards by then, or their RPC or Type Approval will be revoked. Certificates issued under the old standards until that date are only valid to 30 June 2028.

Makers of earbud cases, smartwatch chargers, jump starters, lithium cells and larger battery packs that weren't covered before have just over a year to test and certify. The propagation and functional safety requirements may need evidence that isn't in current test reports. The notice also lets existing VPC certificates or CNS 15364 test reports be converted after gap testing by the original designated lab.


Certification Impact Summary


Area

Before

After

Impact level

Products in scope

Power banks and some lithium battery products under earlier rules

Nine items, including cells, packs to 100 kWh, dedicated chargers and jump starters

High

Power bank standards

Earlier power bank standards

CNS 62133-2 or CNS 62619, plus nail penetration or forced internal short circuit up to 160 Wh

High

Battery systems

Coverage to be confirmed per product

CNS 62133-2 or CNS 62619 below 1 kWh; CNS 62619 for 1–100 kWh

High

Functional safety

To be confirmed against the earlier rules

IEC/UL 60730-1, IEC 61508, ISO 13849 or UL 991/1998 evidence

Medium

Existing power bank certificates

Valid until expiry

Re-issue by 30 June 2028 or revocation

High

RoHS marking

To be confirmed against the earlier rules

Required for power banks, dedicated chargers and jump starters

Medium

Review time

–

14 working days, plus 7 if samples are tested

Low


Timeline and Required Actions


Key Dates


Date

Milestone

17 November 2026

Announcement published and in force; BSMI accepts applications

31 December 2027

Last day for renewals and new applications under the old standards (items 2–9 already covered)

1 January 2028

Mandatory inspection begins for newly added products

30 June 2028

Deadline to re-issue existing power bank certificates

1 July 2028

Old power bank standards no longer apply


Required Actions for Manufacturers


  1. Check which of your lithium products fall under the nine items.

  2. Plan certification for newly covered products before 1 January 2028.

  3. Re-test power banks to the new standards and re-issue certificates by 30 June 2028.

  4. Arrange propagation and functional safety evidence through recognised labs.

  5. Add RoHS content marking where required.

  6. Ask designated labs about converting VPC certificates or CNS 15364 reports.


Conclusion


The expanded Taiwan BSMI lithium battery inspection rules cover far more products than before, from earbud cases to battery systems up to 100 kWh. The 2028 deadlines give time to prepare, but test capacity at designated labs may be tight. GMA Labs and the agency in Taiwan can help plan testing and certification.