Japan's Ministry of Internal Affairs and Communications (MIC) has reformed how space-transmission wireless power transfer (WPT) systems in the 920 MHz band may be deployed. The change does two things: it lifts the long standing indoor only restriction to permit outdoor use within a premises, and it establishes a new, output limited category that can operate without an individual radio station licence. For companies building WPT transmitters and the sensors they power, this reshapes both the market opportunity and the route to certification in Japan.

This article covers the equipment level detail manufacturers, importers, and test labs need. It concerns the 920 MHz space transmission WPT reform specifically not the RFID rules in the same band, which are unchanged.


Regulatory context: what changed and why


Space transmission WPT (Japanese: 空間伝送型ワイヤレス電力伝送), sometimes called "beam WPT," transfers power wirelessly over roughly 5–10 metres and is used to power sensors and low consumption devices in factories, warehouses, care facilities, and building management deployments.


Japan first institutionalized these systems in May 2022, allocating three bands 920 MHz, 2.4 GHz, and 5.7 GHz for indoor only operation under a licensed class known as the wireless power transmission premises radio station (無線電力伝送用構内無線局). The 920 MHz band saw the widest uptake because its lower propagation loss reaches sensors spread across an area and around obstructions.


Two limitations held the technology back: operation was confined indoors, and every installation required a station licence a high hurdle for appliance class or consumer-adjacent products. MIC referred the matter to the Information and Communications Council, which delivered its partial report (答申) on 20 October 2025 setting out the technical conditions for outdoor use and for an output limited, licence free tier. MIC then developed the implementing rules through the Radio Act Enforcement Regulations and an associated specified low power notice; the Radio Regulatory Council concurred on 11 March 2026, public comment ran 14 March–13 April 2026, and MIC published the comment results on 23 June 2026 ahead of finalizing the relevant provisions.


An infographic summarizing regulatory changes to Japan's 920 MHz wireless power transfer rules, including new outdoor use permissions within premises and a license-free tier for devices 250mW or less.

Scope of the reform: two core changes


Outdoor use within a premises is now permitted


The indoor only restriction on 920 MHz WPT premises stations is relaxed so systems may operate outdoors within a controlled premises including partially open spaces such as loading bays, and areas where people come and go subject to safety and interference conditions.


A new licence free "specified low power" WPT tier (≤250 mW)


Alongside the existing licensed stations (which operate up to 1 W), the reform introduces a specified low power radio station (特定小電力無線局) category for WPT. By capping transmitter output at a maximum of 250 mW, these systems can operate without an individual station licence. Delivered power is lower, but removing the licensing step is intended to open the technology to broader, faster deployment including consumer adjacent products already being demonstrated by Japanese manufacturers.


Safety and coexistence conditions


  • RF exposure protection: operation must satisfy Japan's Radio Frequency Protection Guidelines (電波防護指針), with a required cut off so power transfer halts when a person enters a field that would exceed the controlled environment guideline value.

  • Interference coordination: because the 920 MHz band already hosts RFID, active-sensor systems, and LPWA, deployments rely on a coordination scheme (publishing planned deployment information and coordinating with incumbents where concerns arise).

  • Emission limits: the reform sets spurious/unwanted emission allowances for WPT specified low power stations.


What Japan 920 MHz WPT license free rules mean for manufacturers


  1. A lower-friction route to market for WPT transmitters. The ≤250 mW licence-free tier removes the individual station licence step, shortening deployment where per site licensing was previously uneconomic.

  2. Licence free does not mean certification free. A specified low power WPT station is expected to require certified radio equipment (技術基準適合証明, the Giteki mark) from an MIC designated Registered Certification Body (RCB) before market placement. Budget for equipment certification even where no station licence is needed.

  3. Design the transmit stop function in early. RF exposure compliance is enforced through a required cut off. Treat it as a hardware/firmware safety design constraint, not paperwork.

  4. Two tiers, two rulebooks. Higher power (up to 1 W) 920 MHz WPT continues under the licensed premises station regime now with outdoor within premises use available while the new ≤250 mW tier follows the licence free specified low power regime. Confirm which tier a product targets before test planning, because the technical conditions differ.

  5. Coordination obligations sit with deployers but shape product positioning. Manufacturers selling into Japan should be ready to support customers with the technical data those obligations require.

  6. Existing indoor installations are unaffected in their current use, and may be extended outdoors within a premises once compliant with the new conditions.


Certification impact summary


Item

Before this reform

After this reform

Bands in scope

920 MHz / 2.4 GHz / 5.7 GHz (indoor)

Reform applies to 920 MHz (outdoor within premises + new low-power tier)

Where usable

Indoor only

Indoor and outdoor within a premises (conditions apply)

Licensed tier

WPT premises station, up to 1 W, licence required

Unchanged power; outdoor-within-premises use added

Licence-free tier

None

New specified-low-power WPT station, ≤250 mW, no station licence

Equipment certification

Giteki (technical conformity) via RCB

Still required licence free ≠ certification free

RF exposure control

RF Protection Guidelines

RF Protection Guidelines + required transmit-stop function

Coexistence

Indoor coordination

Interference coordination scheme (deployment disclosure/coordination)

RFID (920 MHz)

Licence/registration required

Unchanged not made licence exempt by this reform


Timeline and required actions


Date

Milestone

Status

Required action for industry

May 2022

920/2.4/5.7 GHz WPT institutionalized (indoor, licensed)

Confirmed

Baseline; existing installations continue

20 Oct 2025

Council partial report (答申) on outdoor-use technical conditions

Confirmed

Begin product/roadmap planning for both tiers

11 Mar 2026

Radio Regulatory Council concurs with draft amendments

Confirmed

Confirm draft technical standards; scope test plans

14 Mar–13 Apr 2026

Public comment on specified-low-power notice

Confirmed

23 Jun 2026

Public-comment results published

Confirmed

Finalize certification (Giteki) and transmit stop design

Effective date

Outdoor-within-premises use + ≤250 mW licence-free tier available

confirm exact promulgation/effective date

Align Giteki certification and transmit stop design; brief Japanese customers on coordination obligations